MILESTONE
1:
Project Initiation Activities & Definition of Brief - ACHIEVED
Project task 1 development
activities were completed in November 2001, through project
formulation, 1st PAG Meeting, discussion of initial
proposals for scope of output (prepared for Meeting by TRADA
Technology) and of information retrieval activities e.g. from
Australian Timber Education Package. Development of fully defined brief
for Teaching Package; project publicity, including journal
announcements and Web-posting.
Milestone 2:
Ratified Package Content of Software Specification - ACHIEVED
Project task 2 actions – Review of
Information; User Needs Brief; Software Specification – were completed
in March 2002 through:
- Collating additional
information resources.
- Reviewing other current TRADA
I.T.
- Identifying teaching needs and
student response: FIRST TRIAL WORKSHOP held at Imperial College on the
21/02/02.
- Writing text based software
specification.
- First format PAG review through
first workshop at Imperial College and circulating report.
- TRADA Information Centre
consultation.
Milestone 3:
Alpha Software and Dedicated Project Web Functioning - ACHIEVED.
Project task 3 – Alpha Software
Development – was completed in March 2002 through:
- Developing text, screen layouts
and HTML for dedicated project web.
- Introducing sequential
implementation discipline to software specification.
- Circulating skeletal Alpha
version, demonstrating visual formats, navigation, and overall
structure.
- Writing-in selected technical
content, compiling onto test CD’s.
- Holding university-based
"Tutors plus Students" workshop testing sessions.
- Completing testing of dedicated
project web.
- Second format PAG –
demonstrations and further feedback : scheduled on the 1st
May 2002 at Napier University.
- TRADA Information Centre
consultation.
Milestone 4:
First Stage Beta Development - ACHIEVED.
Project task 4 – Beta 1.0 Draft CD
development – was completed in July 2002 through:
- Bring online dedicated project
web
- Work up more technical content
(ongoing task)
- Produce Draft 1 edition CD -
Beta 1.0 version
- Circulate to PAG
- Generate feedback via
circulation among PAG members
- Write Report 4 (MS04)
letter-style report
- TRADA Information Centre
consultation
Milestone 6:
60% software completion - ACHIEVED.
The milestone schedule was revised
and approved by PO and DTI in January 2003. Original Project Task 5 was
merged into a new Task 6.
Milestone 6 was completed in March
2003 through::
- Reach 60% software completion
- Improve technical content and
collect feedback of PAG members
- Review the dissemination
strategy
- Issue Beta 1.1 software on CD
or any other agreed medium
- PAG meeting
Milestone 7:
Software completion and dissemination - ACHIEVED.
At the 2003 "Time for Timber"
event, approximately 120 copies of the Bete 3.0 Release Version of the
"Timber Design Knowledge" resource were issued to all participants,
with emphasis on encouraging its use amongst universities and colleges.
This interim release was made possible by generous support, additional
to that at initial project planning stages, by the "Wood for Good"
campaign.
Dissemination activities will continue in 2004 to fulfil the final
dissemination plan. "Wood for Good" supported
sessions will take place at selected universities to present and
explain "Timber Design Knowledge" resource.
It is important to recognise the significant and active inputs received
from several universities throughout the UK; leading Consulting
Engineering and Architectural practices, the Professional Institution,
and the "Wood for Good" Campaign. Without these, the achievements would
have been considerably less. The Project Advisory Group's contributions
were outstandingly positive, and these were always followed up by
fulfilment of agreed actions between meetings.

|